WATERWORKS - PHASE II - DETAILED TIMELINE
JULY
07/17/07 Neighborhood Mtg to discuss demolition of Waterworks building and future development of site
07/24/07 Submitted Project Notification form to Massachusetts Historical Commission (MHC) for demolition
AUGUST/SEPTEMBER
08/15/07 Received response from MHC regarding "adverse effect" to demolition
08/20/07 Received letter from HUD regarding adverse effect, deferring to the City of Lynn and Lynn Historical Commission (LHC) for compliance and mediation
August - September Spoke to MHC and LHC to discuss adverse effect
August - September Researched and prepared analysis for MHC & LHC
OCTOBER
10/01/07 Lynn Historical Commission (LHC) Meeting
10/02/07 Mass Historical Commission (MHC) Meeting
10/11/07 Submitted formal response to MHC and LHC
10/29/07 Received approval letter for demolition, agreement and stipulations
NOVEMBER
11/08/07 LCDHC and LHC signed agreement. Forwarded agreement to MHC for signature
11/09/07 RFP for demolition contractor
11/8/2007-11/14/07Researched and contacted photographers for photo documentation
11/13/07 Met with contractor to discuss demolition project
11/14/07 Met with engineer to shoot grades and to determine how much subsurface material needs to be removed for proposed foundations
11/15/07 Met with mason to discuss removal of granite and brick from building
11/16/07 Hired contractor for photo documentation
11/16/07 Met with architect to develop plans for houses on Walnut Street
11/19/07 Entered into contract with demolition contractor
11/26/07 Met with architect to review options
11/27/07 -1/17/08 Demolition Sign Off sheet - contacted utility companies to disconnect utility lines
DECEMBER
12/11/07 Received signed agreement from MHC
12/12/07 Met with architect to discuss project
12/18/07 Met with architect to discuss plans and reuse of building materials
JANUARY
01/11/08 Dig Safe notification and approval
01/23/08 Submitted demolition permit to Inspectional Services Department (ISD)
01/25/08 Met with architect to discuss plans
01/24/08 Photo documentation and research completed
01/25/08 Demolition Permit issued
01/31/08 Pre-construction meeting with demolition contractor and sub contractors
FEBRUARY
02/01/08 Meeting on site plan design with engineer and architect
February 5 -15, 2008 Salvage of building components (i.e. brick, granite, and "Waterworks Sign") to be reused in new construction design for buildings, garden and landscaping
02/07/08 Submitted photo documentation to MHC & LHC in archive boxes
02/08/08 Meeting with architect and engineer to finalize site plan and placement of new buildings
02/12/08 Deadline for site plan
02/13/07 Submit application to Board of Appeals
February 18, 2008 - March 31, 2008 Demolition of building and removal of debris
MARCH
03/03/08 Deadline for site work plans and specifications
03/04/08 RFP for site work
03/11/08 Submit application to Planning Board
03/12/08 Deadline for architect to submit Walnut St. building elevations & draft floor plans
03/13/08 Neighborhood Meeting
03/17/08 RFP for Financing
03/18/08 Site work proposals are due
03/18/08 Board of Appeals Mtg.- City Hall, Rm 302 @ 7:30. Neighbors are encouraged to attend. (tentative)
03/24/08 Enter into contract for site work
03/24/08 Submit building permit applications to ISD & DPW
03/24/08 Apply for Energy Star Program
APRIL
4/1/2008-04/30/08 Site Work begins (estimated timeframe)
04/14/08 Appeal period expires. Notice of Decision may be filed with Registry of Deeds
04/16/08 Deadline for final plans and specifications
04/22/08 Planning Board Meeting, City Hall, Room 302 @ 6:30 (tentative)
MAY
05/01/08 Builders Risk Insurance and close on construction loan
05/19/08 File and record plan at the Registry of Deeds
5/20/2008-06/20/08 Construction begins (estimated timeframe)